Product Well Jumper installation Engineering

Floating units
installation | Offshore et Onshore | Ongoing operations | Team work

 

Product Well Jumper installation Engineering

Client

Bourbon Subsea Services for Total Energies

Dates

2025

Presentation

  • Congo
  • Installation engineering with Bourbon Subsea Services, for the installation of PWJ for TotalEnergies Congo. Including Load out, lifting analysis, rigging and procedures.
  • Quantity: 5
  • Distance to shore : 75 km
  • Water depth: 700 m
  • Project phase: EXE

DVO Services

Engineering consultancy

DV Offshore was in charge of:

  • Pre metrology issue and Post metrology update of following studies.
  • Dynamic lifting analysis review
  • Listing analysis review
  • Rigging design and drawing
  • Mobilisation and installation Procedure